Come By Chance

Status Updates

Schedule
View the project schedule.
Design
-Project Site Plan
-Geotechnical Investigation summary
Construction
-Foundation Installation begins  July 22, 2024
-Tower erection to follow in August 2024
-Tender awarded to Trylon to construct the foundation and erect the tower as of June 24, 2024
Operation
Updates to be posted.

Project Timeline

Site Plan

Tower Fabrication

•100% Complete
•Material delivered to site

May 2024 - Geotechnical Investigation

•Site took 3 days to drill
•Borings were completed at the tower mast and each of the guy anchor locations
•Rock (Rhyolite) was deeper and less competent than expected
•Shallow foundations anticipated

•Frost 1 meter (3.3 feet)
•Groundwater not encountered
•Some near-surface fill from civil works
•Some near-surface peat / organic-lain soils
•A substantial amount of cobbles and boulders
•Seismic Site Class C