Turnkey Gravity Sewer Improvement Program (19,000 LF, Municipal Utility)

Close-up of stacked green PVC gravity sewer pipe with gasketed bell ends, staged for a municipal sewer improvement project.

Project Overview

TEP delivered a turnkey gravity sewer improvement program for a municipal utility in western North Carolina. Spanning roughly 19,000 linear feet of 24-inch PVC gravity sewer, the project included six steel-cased trenchless roadway and highway bores totaling 1,175 linear feet, extensive erosion control, and full site restoration.

The Challenge

The utility needed to expand capacity across a long, high-precision gravity sewer corridor. Key challenges included executing six steel-cased trenchless bores beneath roads and a major highway, managing subsurface rock risks, coordinating multiple stakeholders, meeting public-agency and inclusive procurement requirements, and maintaining strict environmental controls.

The Solution

TEP served as a single point of accountability from estimating through closeout, executing a turnkey construction model:

  • Preconstruction & Estimating: Reviewed plans and specifications to build a detailed, quantity-based estimate and structured the work on a line-item unit-price basis.
  • Inclusive Procurement: Solicited competitive quotes from specialty subcontractors and suppliers while actively promoting disadvantaged, minority-owned, and women-owned business participation through targeted outreach and flexible contract terms.
  • Self-Performed & Trenchless Construction: TEP crews handled open-cut pipe installation, excavation pits, structures, restoration, and site work, while specialized bore partners executed the steel-cased roadway and highway crossings.
  • Risk & Quality Management: Built a defined rock contingency into bore pricing to protect schedules and coordinated testing, inspections, and closeout documentation with the owner and consulting engineer.

The Result

  • Full Corridor Delivery: Approximately 19,000 LF of 24-inch PVC gravity sewer successfully delivered as a cohesive turnkey package.
  • Complex Crossings Completed: Six trenchless steel-cased crossings (~1,175 LF total) completed safely beneath regional roads and a major highway.
  • Environmental Stewardship: Installed and maintained ~19,000 LF of erosion and sediment control alongside the pipeline.
  • Single-Source Accountability & Compliance: Replaced a complex multi-contractor approach with a single accountable partner while fulfilling public-agency inclusive procurement documentation requirements.

TEP Services Provided

  • Construction: Open-cut gravity sewer installation, Trenchless steel-cased bore crossings, Erosion and sediment control, Site restoration
  • Program and Construction Management: Preconstruction estimating, Subcontractor and supplier procurement, Quality control, Public-agency reporting, Closeout administration

Share

Project Services

Program & Construction Management: Budget and schedule management, Material procurement, Quality control, Safety oversight, Inspections & maintenance
Land Development & Management: Erosion and sediment control, Site prep and grading, Ground maintenance
Construction: Utility installations

Project Timeline