Turnkey Gravity Sewer Improvement Program (19,000 LF, Municipal Utility)
Project Overview
TEP delivered a turnkey gravity sewer improvement program for a municipal utility in western North Carolina. Spanning roughly 19,000 linear feet of 24-inch PVC gravity sewer, the project included six steel-cased trenchless roadway and highway bores totaling 1,175 linear feet, extensive erosion control, and full site restoration.
The Challenge
The utility needed to expand capacity across a long, high-precision gravity sewer corridor. Key challenges included executing six steel-cased trenchless bores beneath roads and a major highway, managing subsurface rock risks, coordinating multiple stakeholders, meeting public-agency and inclusive procurement requirements, and maintaining strict environmental controls.
The Solution
TEP served as a single point of accountability from estimating through closeout, executing a turnkey construction model:
- Preconstruction & Estimating: Reviewed plans and specifications to build a detailed, quantity-based estimate and structured the work on a line-item unit-price basis.
- Inclusive Procurement: Solicited competitive quotes from specialty subcontractors and suppliers while actively promoting disadvantaged, minority-owned, and women-owned business participation through targeted outreach and flexible contract terms.
- Self-Performed & Trenchless Construction: TEP crews handled open-cut pipe installation, excavation pits, structures, restoration, and site work, while specialized bore partners executed the steel-cased roadway and highway crossings.
- Risk & Quality Management: Built a defined rock contingency into bore pricing to protect schedules and coordinated testing, inspections, and closeout documentation with the owner and consulting engineer.
The Result
- Full Corridor Delivery: Approximately 19,000 LF of 24-inch PVC gravity sewer successfully delivered as a cohesive turnkey package.
- Complex Crossings Completed: Six trenchless steel-cased crossings (~1,175 LF total) completed safely beneath regional roads and a major highway.
- Environmental Stewardship: Installed and maintained ~19,000 LF of erosion and sediment control alongside the pipeline.
- Single-Source Accountability & Compliance: Replaced a complex multi-contractor approach with a single accountable partner while fulfilling public-agency inclusive procurement documentation requirements.
TEP Services Provided
- Construction: Open-cut gravity sewer installation, Trenchless steel-cased bore crossings, Erosion and sediment control, Site restoration
- Program and Construction Management: Preconstruction estimating, Subcontractor and supplier procurement, Quality control, Public-agency reporting, Closeout administration
Share
Project Services
Project Timeline