Fiber Feasibility Study & Route Engineering for a Southeast Infrastructure Developer

Tracked cable plow installing orange fiber optic conduit along a highway right-of-way, fed from a reel suspended by an excavator as crew members in safety vests guide the line.

Project Overview

TEP delivered a fiber feasibility study and route engineering program for a private fiber infrastructure developer in the Southeast United States. Spanning 150 miles of primary corridor (with 190 additional miles awarded), the study evaluated mixed rights-of-way to provide decision-ready quantities, build-method splits, crossing strategies, and defensible rock-excavation allowances.

The Challenge

The client needed rapid validation of route viability, constructability, and cost across a long-distance underground corridor. Evaluating bore versus plow methods, establishing accurate rock allowances, and planning multi-agency crossings (railroads, pipelines, DOTs, and rivers) required a data-driven approach that transitions directly into design and construction without vendor hand-offs.

The Solution

TEP executed a repeatable, milestone-driven feasibility study designed as the foundational first step toward turnkey delivery:

  • Route Evaluation & Data Collection: Conducted desktop and field evaluations along public rights-of-way to verify terrain and constructability.
  • Pre-Design & Quantity Development: Developed preliminary quantities categorized by build method, crossing type, handhole/vault placement (~1,250 ft spacing), and rock-excavation risk allowances.
  • Options Analysis for Complex Crossings: Evaluated and priced side-by-side alternatives (such as structure attachment versus deep directional bores) for the corridor’s major river crossings.
  • Transparent Feasibility Package: Delivered clear quantities, build-method splits, crossing strategies, and documented assumptions to eliminate fine-print surprises.
  • Program Tracking Setup: Established individual project records within TEP’s tracking platform to monitor schedules and roll up status into a unified program view.
  • Path to Turnkey Execution: Structured the feasibility study to flow seamlessly into TEP’s turnkey design, engineering, permitting, construction, splicing, testing, and as-built closeout services under a single accountable team.

The Result

  • Decision-Ready Long-Haul Feasibility: Provided clear quantities, build-method splits, and crossing strategies for the 150-mile primary route.
  • Informed Risk Management: Delivered side-by-side alternative analyses for complex crossings and established defensible rock-excavation allowances.
  • Expanded Partnership: Earned client confidence, resulting in the award of an additional ~190 miles of feasibility review.
  • Seamless Turnkey Transition: Created a direct, zero-hand-off bridge from feasibility into final engineering, permitting, and construction.

TEP Services Provided

  • Design & Engineering: Fiber feasibility studies, Route evaluation, Pre-design engineering, Quantity development, Crossing strategy design
  • Program and Construction Management: Program setup, Milestone-driven tracking, Risk and schedule management

Share

Project Services

Program & Construction Management: Budget and schedule management
Design & Engineering: Design services, Geotech, Environmental, Fielding and Permitting
Planning & Due Diligence: Feasibility Analyses, Zoning & Permitting

Project Timeline