Multi-Site Network Infrastructure Program (Telecommunications Client)
Project Overview
TEP delivered a turnkey site acquisition, environmental due diligence, design, permitting, utility coordination, equipment management, and construction program for a multi-site network infrastructure rollout spanning multiple U.S. states. Each location required a new secured compound, power for both early turn-up and long-term operation, and fiber connectivity back to the client’s network.
The Challenge
The client needed to expand its network quickly and consistently across geographically dispersed locations, each governed by its own local jurisdiction and utility provider. Every site demanded site acquisition, a full design package, local permits, and a new utility service, while equipment needed to come online before permanent power was available. Varying permitting requirements, dependence on utility timelines, significant site civil work, and the need for clear line of sight at each location all threatened to slow the schedule. The client also required centralized management for ordering and storing their equipment for the West run, along with a single accountable partner and clear visibility into progress across the entire program.
The Solution
We took a full turnkey approach, standardizing our design and construction process across the program while adapting to local code and utility requirements at each site. Our team led utility coordination for new service, delivered temporary power so equipment could be energized ahead of permanent service, managed all permitting and design in-house, and handled end-to-end site acquisition. Additionally, we managed the specialized procurement, ordering, and secure warehousing of the client’s hardware inventory specifically designated for the West run. Weekly status calls and photo documentation kept the client informed throughout. Our teams delivered:
- Site Acquisition & Environmental Due Diligence: Identifying, evaluating, screening, and securing viable candidate locations to support network expansion goals.
- Equipment Management: Ordering, staging, and secure storage management for client equipment supporting the West run.
- Site Civil: Grading, drainage-conscious site prep, gravel surfacing, access improvements, and vegetation clearing for line of sight.
- Compound Security & Grounding: Perimeter fencing and gates, grounding, and required signage.
- Power: New utility service coordination, trenching and conduit, electrical distribution and metering, and temporary and permanent power solutions.
- Fiber: Conduit, fiber installation, termination, and labeling to connect each site to the client’s network.
- Close-out: Inspections, testing, and turn-up of power and connectivity.
The Result
The client gained a single point of accountability for site acquisition, design, permitting, utility coordination, equipment staging, and construction across the full program. A repeatable delivery model kept sites moving through varying jurisdictions and utility timelines, while proactive equipment management for the West run ensured hardware was ready precisely when needed. Furthermore, temporary power solutions allowed the network to keep progressing while permanent service was being delivered.
Services Provided
- Planning & Due Diligence: Site acquisition, site assessment, zoning and permitting, line-of-sight evaluation
- Design & Engineering: Site design packages, civil, electrical, fiber routing
- Logistics & Procurement: Equipment ordering, staging, and secure warehouse storage management
- Program & Construction Management: Schedule management, material procurement, utility coordination, weekly reporting, quality control, safety oversight, inspections
- Construction: Compound civil and fencing, trenching and conduit, electrical and fiber installation, power turn-up